A building permit is not a single request but a chain that moves between an engineering office, an inspection entity, the municipality and an insurer. Knowing the order saves you from moving randomly between parties.

Many project owners start looking for a contractor or begin site work before the engineering documents are complete, and the project stumbles at the first remark from the inspection entity or the municipality. This article explains the sequence of the request on Balady, who handles each stage, and what to prepare in advance, with a reminder that exact conditions and requirements appear on the official platform at the time of applying.

Why the Order of Stages Matters

Each stage depends on the output of the one before it. The municipality cannot review designs that have not been uploaded, and the permit is not valid for use before the defects insurance document is paid. Knowing this sequence helps you distribute tasks early among the owner, the engineering office and the contractor, and anticipate which party the request will return to when there are remarks.

What Is the Building Permit Service on Balady?

It is an electronic service on the Balady platform that allows building works to start under the system after the drawings and engineering documents are completed and approved by accredited engineering offices and the relevant authorities, without visiting the authority. The service page states a service duration of 10 days.

The request itself is electronic, but preparing its engineering files is professional work that needs time and care. The duration mentioned on the service page does not mean the preparatory work is finished on the same day, and your experience may differ depending on how complete the files are and on the remarks of the authorities.

The Stages in Order

  1. The owner, or their representative, authorizes an engineering office to design the project.
  2. The office accepts the authorization in Balady Works, chooses the survey decision, prepares the architectural and structural designs, and uploads the files.
  3. A technical inspection company studies the request to confirm it complies with the Saudi Building Code, and if there are remarks it is returned to the office.
  4. The municipality reviews the request, and upon approval issues the design approval certificate.
  5. The office nominates the supervision office and the contractor, and they approve the assignment.
  6. The defects insurance document is issued and its link is paid.
  7. The municipality fees are paid and the permit is issued, and it is not valid for use before the insurance document is paid.

These stages overlap between several parties, so if one is delayed the effect passes to those after it. It is therefore advisable to follow the status inside the platform and not to wait until the end.

Who Does What

  • The owner: authorizes the engineering office, provides the documents and pays what appears on them in the platform.
  • The engineering office: accepts the authorization, prepares the architectural and structural designs, and uploads the files.
  • The technical inspection company: checks the request against the Saudi Building Code and returns it to the office when there are remarks.
  • The municipality: reviews the request and issues the design approval certificate upon approval.
  • The supervision office and the contractor: approve the assignment nominated by the engineering office.

Coordinating With the Engineering Office

Ask the engineering office to explain the scope of its work, what it will upload in Balady Works and what documents it needs from you, and agree on how to communicate when inspection or municipality remarks arrive. Do not rely on verbal promises alone: document the agreement in writing, and check the authorization status inside the platform yourself.

Coordinating the Contractor and Supervision Office

The engineering office nominates the supervision office and the contractor, and they then approve the assignment. Make sure both know the scope of their work and what will be asked of them in the platform, and that they respond to the assignment on time so that the request does not stall at this stage.

Required Documents

  • An updated electronic title deed, a housing contract, or an investment contract.
  • A valid survey decision for building.
  • A contract with an engineering office for the designs, and a contract with a supervision office and a contractor.
  • The defects insurance document.
  • A soil study report, and a traffic study if required.
  • Declarations, undertakings, and payment of the service fee.

Prepare these documents in an organized file before you start, and make sure the deed or contract and the survey decision are valid, because inconsistent data between documents may lead to remarks that delay the request.

Common Mistakes

  • Treating the permit as ready for use before the defects insurance document is paid.
  • Uploading incomplete or inconsistent files, so the request returns with remarks.
  • Leaving the payment of the link or the fees to the last moment.
  • Not following the status after the request is uploaded and waiting for the parties.
  • Relying on an untrusted intermediary without verifying on the official platform.

After Issuance

The permit data is sent to linked parties such as the electricity and water company, civil defense and the insurance company through integrated services, and this may later ease electricity services and the occupancy certificate.

Keep a copy of the permit, the reports, the design approval certificate and the insurance document in one organized file, as you may need them when dealing with the linked authorities later.

Checklist Before You Start

  • A valid ownership document or contract and a valid survey decision for building.
  • Authorization of the engineering office and its acceptance in Balady Works.
  • Architectural and structural designs consistent with the Saudi Building Code.
  • A soil study report, and a traffic study if required.
  • Nominating the supervision office and the contractor.
  • Arranging payment of the insurance document and the fees shown on the platform.

A General Example

Imagine a landowner who wants to build a house. They begin by authorizing an engineering office and review the documents and the survey decision with it, and the office prepares the designs and uploads them. After the technical inspection remarks, the office amends the files and uploads them again until the municipality reviews them. Then the supervision office and the contractor are nominated, and the insurance document and the fees shown are paid, so the permit is issued. This is a general illustration, not a specific case, and it does not guarantee acceptance of the request or any specific duration.

Following Up After Submission

After submitting, follow the request status regularly through your account, and respond to any remarks through the engineering office. Acceptance and timelines remain with the competent authority.

Frequently Asked Questions

  • Who uploads the designs? The engineering office, after accepting the authorization in Balady Works.
  • Is the permit valid for use as soon as it is issued? No. It is not valid for use before the defects insurance document is paid.
  • What if the request is returned with remarks? The engineering office amends the files according to the remarks and uploads them again.
  • Does this article replace the platform? No. It is general guidance, and the final reference is Balady and the competent authority.

Where Does Professional Follow-Up Help?

A follow-up agent tracks the authorization of the offices, the inspection and municipality remarks, and the payment of fees on time, then hands you the permit and the full reports. You can request the advanced consultation to review your file before you start.

Read also: Electricity connection request • Contractor classification on Balady

Al-Najah Business Services is an independent support entity, not a government body, and does not guarantee acceptance of requests or approvals. Fees and durations are taken from official pages at the time of writing and may change, so verify them before applying.

Al-Najah Business Services is an independent store. Our role is organizational and informational: helping you arrange requirements and follow up. We are not affiliated with any government entity, Zid, or Salla, and we cannot approve designs, issue a permit, or speed it up. To reach us, call 0550604431 or email [email protected].

Al-Najah Business Services: from understanding the market to a decision that drives growth.

Official Sources

This article is general guidance, and the final reference is the competent official authority and its platforms.

You may also like

Google Search Console for Your Store: Steps from Adding It to the Sitemap

Google Search Console for Your Store: Steps from Adding It to the Sitemap

Steps to add your store to Google Search Console, verify ownership, submit a sitemap and follow indexing.

Business & Commercial Register
2026-11-17T17:29:51.088946Z Read more
Common SEO Mistakes in Online Stores: Titles, Descriptions and Images

Common SEO Mistakes in Online Stores: Titles, Descriptions and Images

Common mistakes in a store’s titles, descriptions, images and links, and how to fix them per Google’s guidance.

Business & Commercial Register
2026-11-17T17:29:36.108344Z Read more
Before You Launch Your Zid or Salla Store: A 12-Point Checklist

Before You Launch Your Zid or Salla Store: A 12-Point Checklist

A practical 12-point list to review before launching your Zid or Salla online store.

Business & Commercial Register
2026-11-17T17:29:21.577306Z Read more
E-Invoicing Phase Two: Is My Business Included in the Waves?

E-Invoicing Phase Two: Is My Business Included in the Waves?

How to tell if your business is in the E-Invoicing integration waves, with the criteria for waves 22 to 25.

Business & Commercial Register
2026-11-17T17:28:52.178077Z Read more
Health Insurance for Employees: What an Employer Must Do

Health Insurance for Employees: What an Employer Must Do

What a private-sector employer must provide in health insurance per the Council of Health Insurance, with a checklist.

Business & Commercial Register
2026-11-17T17:28:24.357463Z Read more

Notify me when available

Select option