Occupancy Certificate via Balady: How to Get It After Completion

Occupancy Certificate via Balady: How to Get It After Completion

2026-11-07T13:23:21.179578Z

The building is finished but the services have not been activated? The occupancy certificate may be the missing paper between construction and actually using the building.

What Is an Occupancy Certificate?

The Ministry of Municipalities and Housing has explained that it is an official document confirming the actual completion of the building in line with the licence and the approved requirements, and that it is issued electronically through Balady without visiting the municipalities.

The Steps

  1. Choose the user capacity, then a new request.
  2. Specify the owner type and the applicant type.
  3. Choose the building permit for which the certificate is to be issued.
  4. Choose the engineering office and send the request to it.
  5. The office completes the data and prepares the engineering report.
  6. The municipality approves the certificate after verifying the building on site.
  7. An invoice is issued, and after it is paid the certificate is issued and can be printed.

The Conditions

  • A valid building permit issued six months or more earlier, for which no occupancy certificate has been issued before.
  • Payment of the service fees and any outstanding dues.
  • Contracting an accredited engineering office for non-residential uses.

The Duration

The official service page shows the completion time, which may vary by case, so check it before applying. The Building Compliance Certificate is issued automatically after the occupancy certificate is issued and the fees are paid, with no separate request.

Who Submits the Request?

According to the FAQ published on the Ministry of Municipalities and Housing website, the request is submitted by the beneficiary or by an engineering office authorised by them. The journey on Balady starts by signing in through Absher (Unified National Access), then choosing the owner type and the applicant type. The service page states that it is available to individuals, government entities and establishments.

The Key Attachment: The Technical Report

The request must be accompanied by a technical report from the engineering office explaining the condition of the building and its readiness for occupancy and use. This is why choosing the engineering office is not a formality: it is the office that completes the data and prepares the report on which the municipality's approval is based. The page requires contracting an engineering office for buildings with non-residential use.

A New Building or an Old Licence?

  • New buildings: the certificate is issued after the construction reports (building notifications) are sent through the supervising office.
  • Old licences: they are submitted through the same occupancy certificate service.

So find out which of the two paths applies to your building before you start, and do not assume that the procedure is the same.

Fees: How Do You Find Out?

The service page does not state the amount of the fees; instead it provides a fees calculator. The FAQ explains that you look it up by choosing "Construction Licences service" in the service type tab, then "Occupancy Certificate" in the procedure tab. For that reason we state no amount here: work out your fee from the calculator itself at the time of filing. The page states that payment can be made through Sadad, Visa, Mastercard, Mada and Apple Pay.

Problems That Appear When You Apply

  • The "Complete licence data" message: it appears when the data of an old, transferred licence is incomplete. According to the Ministry, the action is to complete it through the "Correct licence data" service and then apply for the certificate.
  • The licence does not appear: it may have been issued by the municipality and not transferred to Balady. The action is to add it through the supporting services using the "Old building permit" service; it appears for application after the request is approved and the licence is issued.
  • An old certificate without the Balady logo that government bodies reject: submit an issuance request with the new version bearing the Balady logo, from the owner or from the engineering office.

A Separate Unit or the Whole Building?

The FAQ states that the certificate is not issued for a separate unit, but for the entire building linked to the building permit. If you own an apartment or shop inside a building, the right question is: has the certificate been issued for the whole building? Not: how do I get a certificate for my unit?

An Illustrative Example

An illustrative example that does not represent any specific business: the owner of a commercial building finished construction and contracted an engineering office, then started the request and found that the permit had been issued less than six months earlier. Issuance was not possible at that point under the condition, so the owner waited for the period to be completed and meanwhile reviewed outstanding dues and violations. Once the condition was met, the request was submitted, the office prepared the report, the invoice was issued and paid, and the certificate was issued.

A Checklist Before Applying

  1. Make sure the building permit is valid and was issued six months or more ago.
  2. Check that no occupancy certificate has been issued before for this permit.
  3. Pay any outstanding violations and dues.
  4. Choose an engineering office and contract with it if the use is non-residential.
  5. Look up the fees in the fees calculator.
  6. Make sure the permit appears on Balady and that its data is complete.

After the Certificate Is Issued

The Building Compliance Certificate is issued automatically after the occupancy certificate, so you do not submit a separate request for it. The service page states that the beneficiary receives proactive notifications by text message and email, and that related services are available from their dashboard. If a government body asks for the certificate, make sure yours was issued in the version bearing the Balady logo.

What Happens at Each Step?

When you start the request you choose the user capacity and then a new request, specify the owner type and the applicant type, and then choose the building permit for which the certificate is required. You then choose the engineering office and send the request to it. At this point the work moves to the office, which completes the data and prepares the engineering report. The municipality then approves the certificate after verifying the building on site, an invoice with a payment number is issued, and once it is paid the certificate is issued and can be printed. The official page shows the completion time, so check it before applying.

Why Might the Certificate Be Delayed?

  • Six months have not passed since the building permit was issued, a condition that cannot be bypassed according to the FAQ.
  • Unpaid violations or dues.
  • Incomplete data for an old licence transferred to Balady.
  • An incomplete engineering office report.
  • A delay in paying the invoice after the municipality approves the certificate.

Frequently Asked Questions

Can the certificate be issued before six months have passed since the permit?

No. The FAQ states that the certificate cannot be issued before six months have passed from the date the building permit was issued.

Do I need to visit the municipality?

The Ministry has explained that the certificate is issued electronically through Balady without visiting the municipalities, while the municipality's approval after on-site verification remains part of the process.

Do I request the compliance certificate separately?

No. It is issued automatically after the occupancy certificate is issued and the fees are paid.

Common Mistakes Before You Start

  • Believing the certificate is issued for a single apartment or shop inside the building.
  • Applying before six months have passed since the permit.
  • Neglecting to complete the data of an old licence before applying.
  • Choosing an engineering office without confirming it is ready to prepare the technical report.
  • Relying on an old certificate without the Balady logo without checking that the receiving body will accept it.
  • Delaying payment of the invoice after the certificate is approved.

When Should You Review Your File Before Starting?

If your permit is old or transferred from a previous system, if the building has more than one use, or if you are unsure about the status of violations and dues, reviewing the file before applying saves you rounds of returns and amendments. Start by checking that the permit appears on Balady and that its data is complete, then check the four conditions in the Conditions section above.

Where Does Professional Follow-Up Help?

Follow-up prevents the occupancy certificate from stalling because of an outstanding debt or a gap in the engineering office report, and hands you the certificate and the building's other documents ready for services. You can request an advanced consultation to review the status of your file before starting.

Read also: Building permit through Balady • Electricity connection request

Al-Najah Business Services is an independent supporting establishment, not a government entity, and does not guarantee acceptance of applications or approvals. Fees and durations are taken from the official bodies' pages at the time of writing and may change, so verify them before applying.

Al-Najah Business Services: from understanding the market to a decision that drives growth.

Official Sources

This article is general guidance, and the final reference is the competent official body and its platforms.

Steps and conditions to issue an occupancy certificate on Balady and the role of the engineering office.

You may also like

Google Search Console for Your Store: Steps from Adding It to the Sitemap

Google Search Console for Your Store: Steps from Adding It to the Sitemap

Steps to add your store to Google Search Console, verify ownership, submit a sitemap and follow indexing.

Business & Commercial Register
2026-11-17T17:29:51.088946Z Read more
Common SEO Mistakes in Online Stores: Titles, Descriptions and Images

Common SEO Mistakes in Online Stores: Titles, Descriptions and Images

Common mistakes in a store’s titles, descriptions, images and links, and how to fix them per Google’s guidance.

Business & Commercial Register
2026-11-17T17:29:36.108344Z Read more
Before You Launch Your Zid or Salla Store: A 12-Point Checklist

Before You Launch Your Zid or Salla Store: A 12-Point Checklist

A practical 12-point list to review before launching your Zid or Salla online store.

Business & Commercial Register
2026-11-17T17:29:21.577306Z Read more
E-Invoicing Phase Two: Is My Business Included in the Waves?

E-Invoicing Phase Two: Is My Business Included in the Waves?

How to tell if your business is in the E-Invoicing integration waves, with the criteria for waves 22 to 25.

Business & Commercial Register
2026-11-17T17:28:52.178077Z Read more
Health Insurance for Employees: What an Employer Must Do

Health Insurance for Employees: What an Employer Must Do

What a private-sector employer must provide in health insurance per the Council of Health Insurance, with a checklist.

Business & Commercial Register
2026-11-17T17:28:24.357463Z Read more

Notify me when available

Select option